Local Plan 2011-2031 Proposed Submission Draft
Search representations
Results for HNL Sustainable Places, Environment Agency search
New searchObject
Local Plan 2011-2031 Proposed Submission Draft
Policy NE7: Reducing flood risk
Representation ID: 1337
Received: 30/11/2016
Respondent: HNL Sustainable Places, Environment Agency
Legally compliant? Yes
Sound? No
Duty to co-operate? Yes
Object to NE7: Sequential approach not clear
This policy is not currently in line with National Planning Policy Framework (NPPF) or the findings of your Strategic Flood Risk Assessment (SFRA). The sequential approach is not clear in this policy nor the need to locate development outside of medium to high flood risk areas. However, this only requires simple changes to the policy wording to make it sound. In line with your SFRA findings and site specific policies you should strengthen this policy and state that development should be located outside medium to high risk flood areas (flood zone 2 and 3). The sequences outlined in this policy need to be amended to reflect National Guidance: the NPPF and The Planning Practice Guidance: Flood Risk and Coastal Change. It is imperative that you have a robust policy that emphasises the sequential approach to all development in your area.
Object
Local Plan 2011-2031 Proposed Submission Draft
Policy NE10: Water Framework Directive and wastewater infrastructure
Representation ID: 1339
Received: 30/11/2016
Respondent: HNL Sustainable Places, Environment Agency
Legally compliant? Yes
Sound? No
Duty to co-operate? Yes
Object to NE10: Needs to reflect wider Water Framework Directive issues, two separate policies required
We consider this policy is unsound on the grounds of being justified and consistent with national policy. The policy does not adequately reflect on Water Framework Directive (WFD) issues in North Hertfordshire and shows its aspirations for the protection and improvement of its waterbodies overall. The policy to date only makes reference to water quality and water resources aspects of the WFD. We maintain our view that this policy title should be changed to reflect wider WFD issues. We consider that this policy would work better by being separated into two: Water Framework Directive and Wastewater infrastructure. However as this plan is advanced, we suggest that the policy is divided into two sub parts to prevent confusion.
Object
Local Plan 2011-2031 Proposed Submission Draft
Policy NE11: Contaminated land
Representation ID: 1341
Received: 30/11/2016
Respondent: HNL Sustainable Places, Environment Agency
Legally compliant? Yes
Sound? No
Duty to co-operate? Yes
Object to NE11: Does not consider Source Protection Zones, need to secure safe development, tackling unacceptable risks from pollution
We find this policy unsound because it is not consistent with national policy. The policy does consider sensitive locations (Source Protection Zones) or emphasise the requirements for developers and/or landowners to secure a safe development tackling unacceptable risks from pollution. However with a few simple changes and incorporation of our suggested supporting text we can find this policy sound.
Object
Local Plan 2011-2031 Proposed Submission Draft
Policy SP19: Sites EL1, EL2 and EL3 - East of Luton
Representation ID: 1342
Received: 30/11/2016
Respondent: HNL Sustainable Places, Environment Agency
Legally compliant? Yes
Sound? No
Duty to co-operate? Yes
Object to SP19: Historic landfill, further investigations required
We previously highlighted historic landfill featuring on site EL1 but this has not been referred to in the site specific policy SP19.
Object
Local Plan 2011-2031 Proposed Submission Draft
Policy SP17: Site HT1 - Highover Farm, Hitchin
Representation ID: 1346
Received: 30/11/2016
Respondent: HNL Sustainable Places, Environment Agency
Legally compliant? Yes
Sound? No
Duty to co-operate? Yes
Object to Policy SP17: Preliminary Risk Assessment (PRA) required.
Policy SP17: Site HT1
We previously highlighted that a Preliminary Risk Assessment (PRA) would be required but this has not been included.
Object
Local Plan 2011-2031 Proposed Submission Draft
RY9 Land north of York Way
Representation ID: 1350
Received: 30/11/2016
Respondent: HNL Sustainable Places, Environment Agency
Legally compliant? Yes
Sound? No
Duty to co-operate? Yes
Objection to RY9: Proximity to waste sites operating under EA permit
We previously mentioned that there are two waste sites within approximately 150 and 200 metres respectively of RY9. These sites operate under a permit from the Environment Agency. You should be aware that workers/occupiers may have some impacts from these nearby developments, including noise, litter and traffic. As long as the operators of the sites can show that they are complying with the terms of their permits to mitigate these impacts, we would be unlikely to revoke their permit.
Object
Local Plan 2011-2031 Proposed Submission Draft
BA10 Royston Road
Representation ID: 1352
Received: 30/11/2016
Respondent: HNL Sustainable Places, Environment Agency
Legally compliant? Yes
Sound? No
Duty to co-operate? Yes
Object to BA10: Preliminary Risk Assessment (PRA) required
BA10 - Royston Road [Baldock]
We previously highlighted that a Preliminary Risk Assessment (PRA) would be required but this has not been included
Object
Local Plan 2011-2031 Proposed Submission Draft
WY1 Land south of Little Wymondley
Representation ID: 1597
Received: 30/11/2016
Respondent: HNL Sustainable Places, Environment Agency
Legally compliant? Yes
Sound? No
Duty to co-operate? Yes
Object to WY1: Preliminary Risk Assessment and site-specific Flood Risk Assessment required
We have no concerns with this site being allocated providing our previous recommendations are addressed. We previously mentioned that there was Potential contamination from previous uses (farmland) but the requirement for a Preliminary Risk Assessment has not been included within the policy text. While all the proposed development is in Flood Zone 1, you are aware that there is significant Surface water and fluvial flood risk to the proposed access (Stevenage Road) to the site. With this in mind you should strengthen the policy by specifying the need for a site-specific Flood Risk Assessment (FRA) as we previously mentioned
Support
Local Plan 2011-2031 Proposed Submission Draft
LS1 Land at Bedford Road
Representation ID: 1606
Received: 30/11/2016
Respondent: HNL Sustainable Places, Environment Agency
Support for LS1: Modelling required for any development in flood plain
We agree with the policy outlined for this site. If the applicant is looking to build within flood plain they will need to produce a more detailed model for this part of the watercourse as they will need to provide the 1% (1 in 100 year) AEP flood level and the upper central and higher central climate change allowances for the site to produce an appropriate Flood Risk Assessment.
Support
Local Plan 2011-2031 Proposed Submission Draft
Policy NE5: New and improved public open space and biodiversity
Representation ID: 1612
Received: 30/11/2016
Respondent: HNL Sustainable Places, Environment Agency
Support NE5: Previous comments have been incorporated
we support this policy and are satisfied that our previous comments have been incorporated